Process Step | Date Initiated | Date Completed | Comments |
Received | 6/11/1959 | 6/11/1959 |
|
Final Order Issued | 12/28/1959 | 12/28/1959 |
|
CBU Due | 10/1/1968 | 10/1/1968 |
|
Extension FO Issued | 6/5/1980 | 6/5/1980 |
|
Extended Completion Date [Extension C Date] | 10/1/1984 | 10/1/1984 |
|
Extension FO Issued | 11/9/1984 | 11/9/1984 |
|
Extended Completion Date [Extension C Date] | 10/1/1989 | 10/1/1989 |
|
Extension FO Issued | 12/2/1998 | 12/2/1998 |
|
Extension Application Received | 5/12/2009 | 5/12/2009 |
|
Extension FO Issued | 5/18/2009 | 5/18/2009 |
|
Extension FO Issued | 8/7/2019 | 8/7/2019 |
|
ODFW Review | 8/7/2019 | |
|
WMR Request | 8/7/2019 | |
|
Extended Completion Date [Extension C Date] | 10/1/2019 | 10/1/2019 |
|
Certificate Confirming Issued | 3/2/2022 | 3/2/2022 |
|
Extended Completion Date [Extension C Date] | 10/23/2037 | |
|
CBU Due | 10/1/2038 | 10/1/2038 |
|