Process Step | Date Initiated | Date Completed | Comments |
DEQ Review Request | 1/2/2018 | 4/10/2018 |
|
ODFW Review | 1/2/2018 | 2/22/2018 |
|
Received | 1/2/2018 | 1/2/2018 |
|
WMR Request | 1/2/2018 | 4/18/2018 |
|
CW Draft PD | 5/3/2018 | 5/3/2018 |
|
CW Preliminary Determination | 6/18/2018 | 6/18/2018 |
|
CW PD Protest Period | 6/19/2018 | 8/18/2018 |
|
CW Final Order Project Approved | 8/28/2018 | 8/28/2018 |
|
CW Notice of Project Completion Due | 8/28/2018 | 9/1/2020 |
|
CW Project Finalization Due Request | 8/28/2018 | 9/1/2025 |
|
Final Order Issued | 1/21/2021 | 1/21/2021 |
|