Process Step | Date Initiated | Date Completed | Comments |
Received | 9/17/2020 | 9/17/2020 |
|
WMR Request | 9/23/2020 | 10/20/2020 |
|
ODFW Review | 9/23/2020 | 10/27/2020 |
|
DEQ Review Request | 9/23/2020 | |
|
CW Newspaper Funds Requested | 10/1/2020 | 10/26/2020 |
|
CW Newspaper Notice | 11/11/2020 | 11/18/2020 |
|
CW Initial Comment Period | 11/18/2020 | 12/15/2020 |
|
Draft PD Issued | 12/16/2020 | 12/16/2020 |
|
CW PD Protest Period | 2/8/2021 | 4/9/2021 |
|
CW Preliminary Determination | 2/8/2021 | 2/8/2021 |
|
CW Final Order Project Approved | 4/23/2021 | 4/23/2021 |
|
Extension FO Issued | 6/3/2022 | 6/3/2022 |
|
CW Extended Project Completion Deadline | 10/1/2024 | 10/1/2024 |
|