| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/6/2021 | 4/6/2021 |
|
| CW Notice of Project Completion Due | 4/7/2021 | 4/7/2021 |
|
| WMR Request | 4/16/2021 | 5/3/2021 |
|
| CW Newspaper Funds Requested | 4/19/2021 | 4/29/2021 |
|
| CW Newspaper Notice | 5/4/2021 | 5/11/2021 |
|
| CW Initial Comment Period | 5/4/2021 | 6/1/2021 |
|
| CW Draft PD | 6/2/2021 | 6/2/2021 |
|
| CW Preliminary Determination | 6/24/2021 | 6/24/2021 |
|
| CW PD Protest Period | 6/24/2021 | 8/23/2021 |
|
| CW Final Order Project Approved | 8/31/2021 | 8/31/2021 |
|
| CW Final Order Project Completion | 8/31/2021 | 8/31/2021 |
|
| CW Project Finalization Due Request | 8/31/2021 | 11/24/2021 |
|
| Certificate Remaining Issued | 12/6/2021 | 12/6/2021 |
RR 96094 Issued Supersedes Cert 48511
|
| Certificate Remaining Issued | 12/6/2021 | 12/6/2021 |
RR 96095 Issued Supersedes Cert 48511
|
| Certificate Confirming Issued | 12/6/2021 | 12/6/2021 |
CF Cert 96096 Issued Supersedes Cert 48511
|
| CW Finalized | 12/6/2021 | 12/6/2021 |
|