Process Step | Date Initiated | Date Completed | Comments |
Received | 4/14/2021 | 4/14/2021 |
|
WMR Request | 4/16/2021 | 7/2/2021 |
|
CW Newspaper Funds Requested | 5/13/2021 | 5/24/2021 |
|
CW Newspaper Notice | 5/27/2021 | 5/27/2021 |
|
CW Initial Comment Period | 6/1/2021 | 6/24/2021 |
|
ODFW Review | 6/1/2021 | 7/1/2021 |
|
CW Draft PD | 8/2/2021 | 8/2/2021 |
|
CW Preliminary Determination | 9/17/2021 | 9/17/2021 |
|
CW PD Protest Period | 9/17/2021 | 11/16/2021 |
|
CW Final Order Project Approved | 11/22/2021 | 11/22/2021 |
|
CW Final Order Project Completion | 10/19/2023 | 10/19/2023 |
|
Certificate Remaining Issued | 10/21/2024 | 10/21/2024 |
RR 98041 Issued Supersedes Cert 93295
|
Certificate Remaining Issued | 10/21/2024 | 10/21/2024 |
RR 98042 Issued Supersedes Cert 93296
|
CW Finalized | 10/21/2024 | 10/21/2024 |
|