Process Step | Date Initiated | Date Completed | Comments |
Received | 1/23/2023 | 1/23/2023 |
|
WMR Request | 1/25/2023 | 1/30/2023 |
|
CW Newspaper Funds Requested | 2/7/2023 | 2/15/2023 |
|
ODFW Review | 2/28/2023 | 3/9/2023 |
|
CW Initial Comment Period | 3/7/2023 | 3/27/2023 |
|
CW Newspaper Notice | 3/8/2023 | 3/15/2023 |
|
DEQ Review Request | 4/28/2023 | 5/2/2023 |
|
CW Draft PD | 5/3/2023 | 5/11/2023 |
|
CW Draft PD | 5/12/2023 | 5/12/2023 |
Revised DPD
|
CW PD Protest Period | 8/4/2023 | 10/3/2023 |
|
CW Preliminary Determination | 8/4/2023 | 8/4/2023 |
|
CW Final Order Project Approved | 10/11/2023 | 10/11/2023 |
|
CW Final Order Project Completion | 10/11/2023 | 10/11/2023 |
|
CW Extended Project Completion Deadline | 8/9/2024 | 8/9/2024 |
|