| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/26/2023 | 5/26/2023 |
|
| WMR Request | 6/2/2023 | 6/6/2023 |
|
| CW Newspaper Funds Requested | 6/5/2023 | 6/5/2023 |
|
| DEQ Review Request | 6/6/2023 | 6/7/2023 |
|
| CW Newspaper Notice | 6/7/2023 | 6/14/2023 |
|
| CW Draft PD | 7/18/2023 | 7/18/2023 |
|
| CW PD Protest Period | 8/22/2023 | 10/21/2023 |
|
| CW Preliminary Determination | 8/22/2023 | 8/22/2023 |
|
| CW Final Order Project Approved | 10/12/2023 | 10/12/2023 |
|
| CW Extended Project Completion Deadline | 11/17/2023 | 11/17/2023 |
|
| CW Final Order Project Completion | 4/22/2024 | 4/22/2024 |
|
| Certificate Confirming Issued | 4/22/2024 | 4/22/2024 |
Cert 97716 Issued Modifies Cert 95971
|
| CW Finalized | 4/22/2024 | 4/22/2024 |
|