Process Step | Date Initiated | Date Completed | Comments |
Received | 10/13/2023 | 10/13/2023 |
|
WMR Request | 10/17/2023 | 2/13/2024 |
|
ODFW Review | 10/19/2023 | 11/1/2023 |
|
CW Newspaper Funds Requested | 10/23/2023 | 10/26/2023 |
|
CW Initial Comment Period | 11/7/2023 | 12/6/2023 |
|
CW Newspaper Notice | 11/8/2023 | 11/15/2023 |
|
CW Draft PD | 3/12/2024 | 3/12/2024 |
|
CW Preliminary Determination | 5/13/2024 | 5/13/2024 |
|
CW PD Protest Period | 5/13/2024 | 7/12/2024 |
|
CW Finalized | 7/29/2024 | 7/29/2024 |
Order of Approval on Completion and Finalization
|
Certificate Confirming Issued | 7/29/2024 | 7/29/2024 |
CF Cert 97854 Issued Supersedes Cert 83252
|
Certificate Confirming Issued | 7/29/2024 | 7/29/2024 |
CF Cert 97857 Issued Supersedes Cert 83560
|
Certificate Remaining Issued | 7/29/2024 | 7/29/2024 |
RR Cert 97855 Issued Supersedes Cert 83252
|
Certificate Remaining Issued | 7/29/2024 | 7/29/2024 |
RR Cert 97856 Issued Supersedes Cert 83252
|
Certificate Remaining Issued | 7/29/2024 | 7/29/2024 |
RR Cert 97858 Issued Supersedes Cert 83560
|
Certificate Remaining Issued | 7/29/2024 | 7/29/2024 |
RR Cert 97859 Issued Supersedes Cert 83560
|