| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/29/2025 | 9/29/2025 |
|
| WMR Request | 10/6/2025 | 10/15/2025 |
|
| ODFW Review | 10/14/2025 | 11/6/2025 |
|
| News $ Due Letter | 10/14/2025 | 10/22/2025 |
|
| CW Newspaper Notice | 10/25/2025 | 11/1/2025 |
|
| CW Initial Comment Period | 10/28/2025 | 11/18/2025 |
|
| CW Draft PD | 12/3/2025 | 12/3/2025 |
|
| PFO Protest Period | 1/27/2026 | 3/13/2026 |
|
| Proposed Final Order | 1/27/2026 | 1/27/2026 |
|
| Automatic Final Order | 4/15/2026 | 4/15/2026 |
|
| CW Final Order Project Completion | 4/27/2026 | 4/27/2026 |
|
| Certificate Confirming Issued | 4/27/2026 | 4/27/2026 |
CF Cert 98984 Issued Supersedes Cert 17226
|
| Certificate Remaining Issued | 4/27/2026 | 4/27/2026 |
RR Cert 98983 Issued Supersedes Cert 17226
|
| Certificate Remaining Issued | 4/27/2026 | 4/27/2026 |
RR Cert 98985 Issued Supersedes Cert 17226
|
| CW Finalized | 4/27/2026 | 4/27/2026 |
|