Process Step | Date Initiated | Date Completed | Comments |
Received | 11/5/2009 | 11/5/2009 |
|
CW Preliminary Determination | 2/10/2012 | 2/10/2012 |
|
CW Final Order Project Approved | 4/24/2012 | 4/24/2012 |
|
CW Final Order Project Approved | 1/27/2015 | 1/27/2015 |
|
CW Final Order Project Completion | 1/27/2015 | 1/27/2015 |
|
Certificate Confirming Issued | 1/27/2015 | 1/27/2015 |
Cert 89859 issued to confirm the Instream Water Right portion
|
Certificate Remaining Issued | 1/27/2015 | 1/27/2015 |
Reduced RR Cert 89856 issued supersedes Cert 85285; Reduced RR Cert 89858 issued supersedes Cert 80773; RR Cert 89857 issued supersedes Cert 80773
|
CW Finalized | 1/27/2015 | 1/27/2015 |
|
CW Notice of Use/Disposition | 2/6/2020 | 2/6/2020 |
|
CW Notice of Use/Disposition | 1/28/2021 | 1/28/2021 |
|
CW Use/Disp Order | 3/5/2021 | 3/5/2021 |
|
CW Use/Disp Order | 3/7/2022 | 3/7/2022 |
|
Final Order Issued | 7/8/2022 | 7/8/2022 |
|
CW Use/Disp Order | 2/13/2023 | 2/13/2023 |
|