| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/24/2011 | 2/24/2011 |
|
| WMR Request | 3/11/2011 | 5/23/2012 |
|
| CW Initial Comment Period | 5/1/2012 | 5/22/2012 |
|
| CW Newspaper Notice | 5/12/2012 | 6/11/2012 |
|
| CW Draft PD | 2/6/2013 | 2/6/2013 |
|
| CW Preliminary Determination | 2/13/2013 | 2/13/2013 |
|
| CW Finalized | 4/16/2013 | 4/16/2013 |
|
| CW Final Order Project Approved | 4/16/2013 | 4/16/2013 |
|
| CW Final Order Project Completion | 4/16/2013 | 4/16/2013 |
|
| Certificate Confirming Issued | 12/3/2014 | 12/3/2014 |
|
| Certificate Confirming Issued | 12/3/2014 | 12/3/2014 |
|
| Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|