Process Step | Date Initiated | Date Completed | Comments |
Received | 4/8/2015 | 4/8/2015 |
|
WMR Request | 4/10/2015 | 5/21/2015 |
|
ODFW Review | 4/15/2015 | 5/21/2015 |
|
CW Draft PD | 6/5/2015 | 6/5/2015 |
|
CW Preliminary Determination | 6/16/2015 | 6/16/2015 |
|
CW PD Protest Period | 6/18/2015 | 8/17/2015 |
|
CW Final Order Project Approved | 8/18/2015 | 8/18/2015 |
|
Project Finalization Due | 8/18/2015 | 6/30/2025 |
|
CW Notice of Project Completion Due | 6/30/2020 | 9/30/2023 |
|
Extension FO Issued | 9/22/2021 | 9/22/2021 |
|
Certificate Remaining Issued | 10/21/2024 | 10/21/2024 |
RR 98057 Issued Supersedes Cert 45888
|
Certificate Remaining Issued | 10/21/2024 | 10/21/2024 |
RR 98058 Issued Supersedes Cert 45888
|
CW Final Order Project Completion | 10/21/2024 | 10/21/2024 |
|
Certificate Confirming Issued | 10/21/2024 | 10/21/2024 |
CF Cert 98059 Issued Supersedes Cert 45888
|
CW Finalized | 10/21/2024 | 10/21/2024 |
|