| Process Step | Date Initiated | Date Completed | Comments |
| Received | 11/18/2016 | 11/18/2016 |
|
| WMR Request | 11/21/2016 | 12/20/2016 |
|
| ODFW Review | 11/21/2016 | 11/29/2016 |
|
| CW Newspaper Funds Requested | 12/16/2016 | 1/11/2016 |
|
| CW Initial Comment Period | 1/3/2017 | 1/31/2017 |
|
| CW Newspaper Notice | 1/4/2017 | 1/4/2017 |
Run 1/4/2017 & 1/11/2017 - Wallowa Chieftan
|
| CW Draft PD | 1/10/2017 | 2/7/2017 |
|
| CW Preliminary Determination | 2/7/2017 | 2/7/2017 |
|
| CW PD Protest Period | 2/9/2017 | 4/10/2017 |
|
| CW Final Order Project Approved | 4/11/2017 | 4/11/2017 |
|
| CW Notice of Project Completion Due | 4/11/2017 | 12/18/2017 |
|
| CW Project Finalization Due Request | 4/11/2017 | 12/18/2017 |
|
| CW Final Order Project Completion | 1/8/2018 | |
|
| CW Finalized | 1/8/2018 | 1/8/2018 |
|
| CBU Received | 4/12/2019 | 4/12/2019 |
|
| Certificate Confirming Issued | 9/26/2019 | 9/26/2019 |
|