Process Step | Date Initiated | Date Completed | Comments |
Received | 9/6/2005 | 9/6/2005 |
|
Reimbursement Authority | 9/12/2005 | 9/12/2005 |
|
WMR Request | 9/12/2005 | 9/15/2005 |
|
GW Review Request | 9/12/2005 | 1/9/2006 |
|
Transfer Initial Comment Period | 9/20/2005 | 9/20/2005 |
|
RA Applicant Agreement | 10/6/2005 | 10/6/2005 |
Work Order #: R05-025W
|
Draft PD Issued | 1/20/2006 | 1/20/2006 |
|
GW Review Request | 8/28/2008 | 10/9/2008 |
|
Draft PD Issued | 11/19/2008 | 11/19/2008 |
|
PD Issued | 12/23/2008 | 12/23/2008 |
|
PD Weekly Public Notice | 12/30/2008 | 12/30/2008 |
|
Final Order Issued | 2/27/2009 | 2/27/2009 |
|
Final Order Issued | 8/8/2011 | 8/8/2011 |
|
CBU Received | 10/31/2012 | 10/31/2012 |
|
Final Order Issued | 5/6/2014 | 5/6/2014 |
|
Certificate Confirming Issued | 5/20/2014 | 5/20/2014 |
Cert 89266, with Cert 87206, supersedes Cert 41536
|
Completion Due (C Date) | 10/1/2014 | 10/1/2014 |
|
CBU Due | 10/1/2015 | 10/1/2015 |
|