| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/7/2005 | 12/7/2005 |
|
| Transfer Initial Comment Period | 12/13/2005 | 12/13/2005 |
|
| WMR Request | 12/14/2005 | 12/16/2005 |
|
| ODFW Review | 12/14/2005 | 4/11/2006 |
|
| Draft PD Issued | 4/14/2006 | 4/14/2006 |
|
| PD Newspaper Notice | 6/28/2006 | 6/28/2006 |
|
| PD Issued | 6/28/2006 | 6/28/2006 |
|
| PD Weekly Public Notice | 7/11/2006 | 7/11/2006 |
|
| Final Order Issued | 9/22/2006 | 9/22/2006 |
|
| Completion Due (C Date) | 10/1/2007 | 10/1/2007 |
|
| CBU Received | 5/2/2008 | 5/2/2008 |
|
| CBU Due | 10/1/2008 | 10/1/2008 |
|
| Proposed Certificate Mailing | 11/7/2008 | 11/7/2008 |
|
| Certificate Confirming Issued | 1/27/2009 | 1/27/2009 |
|