Process Step | Date Initiated | Date Completed | Comments |
Received | 3/14/2006 | 3/14/2006 |
|
Transfer Initial Comment Period | 3/21/2006 | 3/21/2006 |
|
WMR Request | 3/21/2006 | 5/12/2006 |
|
Draft PD Issued | 11/20/2006 | 11/20/2006 |
|
Administrative Hold | 6/21/2007 | 7/31/2008 |
|
GW Review Request | 9/14/2009 | 12/21/2009 |
|
WMR Request | 9/14/2009 | 10/23/2009 |
|
Draft PD Issued | 10/7/2011 | 10/7/2011 |
|
PD Issued | 11/15/2011 | 11/15/2011 |
|
PD Weekly Public Notice | 11/22/2011 | 11/22/2011 |
|
Final Order Issued | 1/13/2012 | 1/13/2012 |
|
Certificate Remaining Issued | 1/18/2012 | |
RR 87252 issued supersededs Cert 36903
|
Certificate Remaining Issued | 1/18/2012 | |
RR 83618 issued supersededs Cert 57883
|
Certificate Remaining Issued | 1/18/2012 | |
RR 87523 issued supersedes Cert 57884
|
Certificate Remaining Issued | 8/14/2012 | 8/14/2012 |
RR 87253 issued to correct Cert 87523; supersedes original Cert 57884
|
Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
CBU Due | 10/1/2014 | 10/1/2014 |
|
CBU Received | 7/20/2015 | 7/20/2015 |
|
Proposed Certificate Mailing | 10/18/2016 | 10/18/2016 |
|
Certificate Confirming Issued | 12/2/2016 | 12/2/2016 |
|