Process Step | Date Initiated | Date Completed | Comments |
Received | 4/11/2006 | 4/11/2006 |
|
Reimbursement Authority | 4/12/2006 | 4/12/2006 |
|
GW Review Request | 4/13/2006 | 6/1/2006 |
|
WMR Request | 4/13/2006 | 4/17/2006 |
|
Transfer Initial Comment Period | 4/18/2006 | 4/18/2006 |
|
RA Applicant Agreement | 7/6/2006 | 7/6/2006 |
Work Order #: R07-071F
|
Draft PD Issued | 7/26/2006 | 7/26/2006 |
|
PD Issued | 10/5/2007 | 10/5/2007 |
|
PD Weekly Public Notice | 10/9/2007 | 10/9/2007 |
|
Final Order Issued | 11/14/2007 | 11/14/2007 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
Extension Application Received | 11/29/2011 | 11/29/2011 |
|
Extension FO Issued | 12/23/2011 | 12/23/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
CBU Received | 2/27/2020 | 2/27/2020 |
|
Certificate Confirming Issued | 5/26/2020 | 5/26/2020 |
|
Completion Due (C Date) | 10/1/2036 | 10/1/2036 |
|
CBU Due | 10/1/2037 | 10/1/2037 |
|