| Process Step | Date Initiated | Date Completed | Comments |
| Reimbursement Authority | 10/19/2005 | |
|
| Received | 4/17/2006 | 4/17/2006 |
|
| ODFW Review | 4/27/2006 | 11/21/2006 |
|
| WMR Request | 4/27/2006 | 5/3/2006 |
|
| Transfer Initial Comment Period | 5/2/2006 | 5/2/2006 |
|
| RA Applicant Agreement | 6/23/2006 | 6/23/2006 |
Work Order #: R07-073I
|
| Deficiency Letter | 4/30/2007 | |
|
| Deficiency Letter | 2/11/2008 | |
|
| Deficiency Letter | 3/20/2008 | |
|
| Deficiency Letter | 6/18/2008 | |
|
| Draft PD Issued | 8/13/2008 | 8/13/2008 |
|
| PD Issued | 9/8/2008 | 9/8/2008 |
|
| PD Weekly Public Notice | 9/9/2008 | 9/9/2008 |
|
| Final Order Issued | 11/6/2008 | 11/6/2008 |
|
| Certificate Remaining Issued | 11/6/2008 | 11/6/2008 |
|
| Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
| CBU Received | 10/13/2010 | 10/13/2010 |
|
| CBU Due | 10/1/2011 | 10/1/2011 |
|
| Proposed Certificate Mailing | 5/9/2014 | 5/9/2014 |
|
| Certificate Confirming Issued | 8/29/2014 | 8/29/2014 |
|