Process Step | Date Initiated | Date Completed | Comments |
Received | 4/26/2006 | 4/26/2006 |
|
Transfer Initial Comment Period | 5/9/2006 | 5/9/2006 |
|
WMR Request | 5/25/2006 | 6/6/2006 |
|
ODFW Review | 5/25/2006 | 6/5/2006 |
|
Reimbursement Authority | 6/16/2006 | 6/5/2007 |
|
RA Applicant Agreement | 7/20/2006 | 7/20/2006 |
Work Order #: R07-070H
|
Draft PD Issued | 8/10/2006 | 8/10/2006 |
|
PD Issued | 3/28/2007 | 3/28/2007 |
|
PD Newspaper Notice | 3/28/2007 | 3/28/2007 |
|
PD Weekly Public Notice | 4/3/2007 | 4/3/2007 |
|
Final Order Issued | 6/5/2007 | 6/5/2007 |
|
Proposed Certificate Mailing | 9/24/2008 | 9/24/2008 |
|
Proposed Certificate Mailing | 1/2/2009 | |
|
Certificate Confirming Issued | 3/20/2009 | 3/20/2009 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|
Certificate Confirming Issued | 2/12/2015 | 2/12/2015 |
CF 89864 issued supersedes 85409
|