Process Step | Date Initiated | Date Completed | Comments |
Received | 6/2/2006 | 6/2/2006 |
|
Reimbursement Authority | 6/2/2006 | 1/31/2007 |
|
GW Review Request | 6/6/2006 | 9/15/2006 |
|
WMR Request | 6/6/2006 | 6/13/2006 |
|
Transfer Initial Comment Period | 6/13/2006 | 6/13/2006 |
|
RA Applicant Agreement | 6/21/2006 | 6/21/2006 |
Work Order #: R07-075K
|
Deficiency Letter | 8/8/2006 | |
|
Draft PD Issued | 9/28/2006 | 9/27/2006 |
|
PD Issued | 11/30/2006 | 11/30/2006 |
|
PD Newspaper Notice | 11/30/2006 | 11/30/2006 |
|
PD Weekly Public Notice | 12/5/2006 | 12/5/2006 |
|
Final Order Issued | 1/31/2007 | 1/31/2007 |
|
Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
CBU Received | 9/30/2009 | 9/30/2009 |
|
CBU Due | 10/1/2009 | 10/1/2009 |
|
Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
CBU Due | 10/1/2011 | 10/1/2011 |
|
Extension Application Received | 10/14/2016 | |
|
Extension FO Issued | 11/21/2016 | 11/21/2016 |
|
Certificate Confirming Issued | 3/10/2017 | 3/10/2017 |
|