Process Step | Date Initiated | Date Completed | Comments |
Received | 7/3/2006 | 7/3/2006 |
|
Reimbursement Authority | 7/3/2006 | 8/14/2007 |
|
Transfer Initial Comment Period | 7/11/2006 | 7/11/2006 |
|
WMR Request | 7/11/2006 | 7/19/2006 |
|
ODFW Review | 7/11/2006 | 8/4/2006 |
|
RA Applicant Agreement | 7/26/2006 | 7/26/2006 |
Work Order #: R07-075M
|
Draft PD Issued | 9/6/2006 | 9/6/2006 |
|
Draft PD Issued | 8/14/2007 | 8/14/2007 |
|
PD Issued | 10/1/2007 | 10/1/2007 |
|
PD Weekly Public Notice | 10/2/2007 | 10/2/2007 |
|
Final Order Issued | 2/26/2008 | 2/26/2008 |
|
Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
CBU Received | 10/19/2009 | 10/19/2009 |
|
CBU Due | 10/1/2010 | 10/1/2010 |
|
Certificate Confirming Issued | 8/9/2013 | 8/9/2013 |
|