Process Step | Date Initiated | Date Completed | Comments |
Received | 11/17/2006 | 11/17/2006 |
|
ODFW Review | 11/21/2006 | 12/7/2006 |
|
WMR Request | 11/21/2006 | 11/27/2006 |
|
Transfer Initial Comment Period | 11/28/2006 | 11/28/2006 |
|
GW Review Request | 12/28/2006 | 1/27/2007 |
|
Deficiency Letter | 1/11/2007 | 1/25/2007 |
|
Deficiency Letter | 1/25/2007 | 3/13/2007 |
|
GW Review Request | 3/19/2007 | 4/23/2007 |
|
Deficiency Letter | 3/21/2007 | 3/21/2007 |
|
Draft PD Issued | 6/25/2007 | 6/25/2007 |
|
PD Issued | 8/17/2007 | 8/17/2007 |
|
PD Weekly Public Notice | 8/21/2007 | 8/21/2007 |
|
Final Order Issued | 9/27/2007 | 9/27/2007 |
|
Completion Due (C Date) | 10/1/2008 | 10/1/2008 |
|
CBU Due | 10/1/2009 | 10/1/2009 |
|