| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/28/2007 | 2/28/2007 |
|
| WMR Request | 3/8/2007 | 7/11/2007 |
|
| GW Review Request | 3/8/2007 | 4/4/2007 |
|
| Transfer Initial Comment Period | 3/13/2007 | 3/13/2007 |
|
| Draft PD Issued | 5/22/2007 | 5/22/2007 |
|
| PD Issued | 7/18/2007 | 7/18/2007 |
|
| PD Weekly Public Notice | 7/24/2007 | 7/24/2007 |
|
| Final Order Issued | 10/17/2007 | 10/17/2007 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|
| CBU Received | 9/5/2017 | 9/5/2017 |
|
| Certificate Confirming Issued | 9/24/2021 | 9/24/2021 |
|