| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/6/2007 | 4/6/2007 |
|
| Transfer Initial Comment Period | 4/10/2007 | 4/10/2007 |
|
| WMR Request | 4/13/2007 | 5/10/2007 |
|
| GW Review Request | 4/13/2007 | 7/5/2007 |
|
| Draft PD Issued | 1/14/2009 | 1/14/2009 |
|
| PD Issued | 7/24/2009 | 7/24/2009 |
|
| PD Weekly Public Notice | 7/28/2009 | 7/28/2009 |
|
| Final Order Issued | 12/7/2009 | 12/7/2009 |
|
| Certificate Remaining Issued | 12/7/2009 | |
RR Cert 85400 issued supersedes Cert 15532
RR Cert 85401 issued supersedes Cert 15532
|
| Completion Due (C Date) | 10/1/2015 | 10/1/2015 |
|
| CBU Received | 8/29/2016 | 8/29/2016 |
|
| CBU Due | 10/1/2016 | 10/1/2016 |
|
| Certificate Confirming Issued | 1/28/2022 | 1/28/2022 |
|