| Process Step | Date Initiated | Date Completed | Comments |
| Received | 8/6/2007 | 8/6/2007 |
|
| Reimbursement Authority | 8/6/2007 | 8/31/2009 |
|
| WMR Request | 8/10/2007 | 9/14/2007 |
|
| ODFW Review | 8/10/2007 | 9/6/2007 |
|
| Transfer Initial Comment Period | 8/14/2007 | 8/14/2007 |
|
| Reimbursement Authority | 4/28/2008 | 8/31/2009 |
|
| Transfer Initial Comment Period | 4/29/2008 | 4/29/2008 |
|
| RA Applicant Agreement | 6/23/2008 | 6/23/2008 |
|
| WMR Request | 7/25/2008 | 7/25/2008 |
|
| Draft PD Issued | 5/11/2009 | 5/11/2009 |
|
| PD Issued | 7/22/2009 | 7/22/2009 |
|
| PD Weekly Public Notice | 7/28/2009 | 7/28/2009 |
|
| Certificate Remaining Issued | 8/31/2009 | |
RR Cert 85782 issued supersedes Cert 39173
RR Cert 85783 issued supersedes Cert 27051
|
| Final Order Issued | 8/31/2009 | 8/31/2009 |
|
| Completion Due (C Date) | 10/1/2014 | 10/1/2014 |
|
| CBU Due | 10/1/2015 | 10/1/2015 |
|