| Process Step | Date Initiated | Date Completed | Comments |
| Received | 9/14/2007 | 9/14/2007 |
|
| Reimbursement Authority | 9/14/2007 | 3/24/2008 |
|
| Transfer Initial Comment Period | 9/25/2007 | 9/25/2007 |
|
| WMR Request | 10/4/2007 | 10/16/2007 |
|
| ODFW Review | 10/4/2007 | 12/21/2007 |
|
| RA Applicant Agreement | 11/29/2007 | 11/29/2007 |
Work Order #: R09-074T
|
| Draft PD Issued | 12/31/2007 | 12/31/2007 |
|
| PD Issued | 1/28/2008 | 1/28/2008 |
|
| PD Newspaper Notice | 1/30/2008 | 3/21/2008 |
|
| PD Weekly Public Notice | 2/5/2008 | 2/5/2008 |
|
| Final Order Issued | 3/25/2008 | 3/25/2008 |
|
| Extension FO Issued | 9/23/2009 | 9/23/2009 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| CBU Received | 1/31/2020 | 1/31/2020 |
|