| Process Step | Date Initiated | Date Completed | Comments |
| Received | 10/3/2007 | 10/3/2007 |
|
| Reimbursement Authority | 10/3/2007 | 3/24/2008 |
|
| WMR Request | 10/10/2007 | 10/16/2007 |
|
| Transfer Initial Comment Period | 10/16/2007 | 10/16/2007 |
|
| RA Applicant Agreement | 11/5/2007 | 11/5/2007 |
Work Order #: R09-73AC
|
| ODFW Review | 11/21/2007 | 12/20/2007 |
|
| Draft PD Issued | 12/26/2007 | 12/26/2007 |
|
| PD Issued | 1/28/2008 | 1/28/2008 |
|
| PD Newspaper Notice | 1/30/2008 | 1/30/2008 |
|
| PD Weekly Public Notice | 2/5/2008 | 2/5/2008 |
|
| Final Order Issued | 3/25/2008 | 3/25/2008 |
|
| Completion Due (C Date) | 10/1/2009 | 10/1/2009 |
|
| CBU Due | 10/1/2010 | 10/1/2010 |
|
| CBU Received | 12/15/2011 | 12/15/2011 |
|
| Certificate Confirming Issued | 12/9/2016 | 12/9/2016 |
|