| Process Step | Date Initiated | Date Completed | Comments |
| Received | 12/17/2007 | 12/17/2007 |
|
| Reimbursement Authority | 12/20/2007 | 12/20/2007 |
|
| WMR Request | 12/20/2007 | 1/2/2008 |
|
| GW Review Request | 12/20/2007 | 12/24/2007 |
|
| Transfer Initial Comment Period | 12/25/2007 | 12/25/2007 |
|
| Draft PD Issued | 4/6/2009 | 4/6/2009 |
|
| PD Issued | 7/24/2009 | 7/24/2009 |
|
| PD Weekly Public Notice | 7/28/2009 | 7/28/2009 |
|
| Final Order Issued | 9/23/2009 | 9/23/2009 |
|
| CBU Received | 8/17/2010 | 8/17/2010 |
|
| Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
| CBU Due | 10/1/2011 | 10/1/2011 |
|
| Certificate Remaining Issued | 2/4/2020 | 2/4/2020 |
RR Cert 94898 Issued Supersedes Cert 47725
|
| Certificate Confirming Issued | 10/13/2023 | 10/13/2023 |
|