Process Step | Date Initiated | Date Completed | Comments |
Received | 12/19/2007 | 12/19/2007 |
|
Transfer Initial Comment Period | 12/25/2007 | 12/25/2007 |
|
WMR Request | 12/28/2007 | 1/8/2008 |
|
Draft PD Issued | 8/20/2009 | 8/20/2009 |
|
PD Issued | 9/25/2009 | 9/25/2009 |
|
PD Weekly Public Notice | 9/29/2009 | 9/29/2009 |
|
Final Order Issued | 11/4/2009 | 11/4/2009 |
|
CBU Received | 3/29/2011 | 3/29/2011 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Certificate Confirming Issued | 6/20/2013 | 6/20/2013 |
|