| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/15/2008 | 2/15/2008 |
|
| WMR Request | 2/25/2008 | 2/27/2008 |
|
| Transfer Initial Comment Period | 2/26/2008 | 2/26/2008 |
|
| Draft PD Issued | 11/20/2008 | 11/20/2008 |
|
| PD Issued | 3/25/2009 | 3/25/2009 |
|
| PD Weekly Public Notice | 4/7/2009 | 4/7/2009 |
|
| Final Order Issued | 5/18/2009 | 5/18/2009 |
|
| Certificate Remaining Issued | 5/18/2009 | |
|
| Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
| CBU Due | 10/1/2011 | 10/1/2011 |
|
| Extension Application Received | 8/25/2017 | |
|
| Extension FO Issued | 9/27/2017 | 9/27/2017 |
|
| CBU Received | 9/30/2019 | 9/30/2019 |
|
| Certificate Confirming Issued | 4/28/2023 | 4/28/2023 |
|