Process Step | Date Initiated | Date Completed | Comments |
Received | 2/21/2008 | 2/21/2008 |
|
WMR Request | 3/3/2008 | 3/26/2008 |
|
Transfer Initial Comment Period | 3/4/2008 | 3/4/2008 |
|
Deficiency Letter | 8/29/2009 | 8/29/2009 |
|
Deficiency Letter | 10/1/2009 | 10/1/2009 |
|
Draft PD Issued | 12/10/2009 | 12/10/2009 |
|
PD Issued | 1/15/2010 | 1/15/2010 |
|
PD Weekly Public Notice | 1/26/2010 | 1/26/2010 |
|
Final Order Issued | 2/26/2010 | 2/26/2010 |
|
Certificate Remaining Issued | 2/26/2010 | 2/26/2010 |
RR Cert 86023 issued supersedes Cert 31147
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Certificate Remaining Issued | 6/3/2019 | 6/3/2019 |
RR 94392 Issued Supersedes Cert 973
|