| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/18/2008 | 3/18/2008 |
|
| WMR Request | 3/28/2008 | 5/27/2008 |
|
| ODFW Review | 3/28/2008 | 4/14/2008 |
|
| Transfer Initial Comment Period | 4/1/2008 | 4/1/2008 |
|
| Reimbursement Authority | 4/28/2008 | 9/3/2009 |
|
| RA Applicant Agreement | 2/25/2009 | 2/25/2009 |
Work Order #: R09 135 09
|
| Draft PD Issued | 4/1/2009 | 4/1/2009 |
|
| PD Issued | 6/11/2009 | 6/11/2009 |
|
| PD Weekly Public Notice | 6/16/2009 | 6/16/2009 |
|
| Certificate Remaining Issued | 9/3/2009 | |
RR Cert 85590 issued supersedes Cert 25578
RR Cert 85591 issued supersedes Cert 32299
RR Cert 85592 issued supersedes Cert 51510
|
| Final Order Issued | 9/3/2009 | 9/3/2009 |
|
| Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
| Extension FO Issued | 8/23/2011 | 8/23/2011 |
|
| CBU Due | 10/1/2011 | 10/1/2011 |
|
| Extension Application Received | 9/28/2012 | 9/28/2012 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| Completion Due (C Date) | 10/15/2012 | 10/1/2014 |
|
| Extension FO Issued | 10/15/2012 | 10/15/2012 |
|
| Extension Application Received | 12/22/2014 | 12/22/2014 |
|
| Extension FO Issued | 4/20/2015 | 4/20/2015 |
|
| Completion Due (C Date) | 10/1/2020 | 10/1/2020 |
|
| CBU Due | 10/1/2021 | 10/1/2021 |
|