| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/24/2008 | 3/24/2008 |
|
| Transfer Initial Comment Period | 4/8/2008 | 4/8/2008 |
|
| WMR Request | 4/8/2008 | 4/21/2008 |
|
| Draft PD Issued | 4/15/2010 | 4/15/2010 |
|
| PD Issued | 6/9/2010 | 6/9/2010 |
|
| PD Newspaper Notice | 6/11/2010 | |
|
| PD Weekly Public Notice | 6/15/2010 | 6/15/2010 |
|
| Final Order Issued | 8/23/2010 | 8/23/2010 |
|
| Certificate Remaining Issued | 8/23/2010 | |
RR Cert 86498 issued supercedes Cert 30441
RR Cert 86499 issued supercedes Cert 29711
|
| CBU Received | 12/6/2010 | 12/6/2010 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Certificate Confirming Issued | 10/4/2013 | 10/4/2013 |
|