| Process Step | Date Initiated | Date Completed | Comments |
| Received | 7/23/2008 | 7/23/2008 |
|
| WMR Request | 8/1/2008 | 8/22/2008 |
|
| ODFW Review | 8/1/2008 | 9/24/2008 |
|
| Transfer Initial Comment Period | 8/5/2008 | 8/5/2008 |
|
| Draft PD Issued | 9/11/2009 | 9/11/2009 |
|
| PD Issued | 10/23/2009 | 10/23/2009 |
|
| PD Weekly Public Notice | 10/27/2009 | 10/27/2009 |
|
| Final Order Issued | 12/30/2009 | 12/30/2009 |
|
| Certificate Remaining Issued | 12/30/2009 | |
RR Cert 85981 issued supersedes Cert 83265
|
| Certificate Remaining Issued | 3/12/2010 | |
Correcting Cert 86120 issued supersedes Cert 85981
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Received | 5/9/2012 | 5/9/2012 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Certificate Confirming Issued | 9/13/2013 | 9/13/2013 |
|