Process Step | Date Initiated | Date Completed | Comments |
Transfer Initial Comment Period | 12/16/2008 | 12/16/2008 |
|
WMR Request | 12/19/2008 | 12/22/2008 |
|
Received | 12/19/2008 | 12/19/2008 |
|
GW Review Request | 12/19/2008 | 2/20/2009 |
|
Reimbursement Authority | 2/24/2009 | 5/8/2009 |
|
RA Applicant Agreement | 3/9/2009 | 3/9/2009 |
|
Draft PD Issued | 3/18/2009 | 3/18/2009 |
|
PD Issued | 3/31/2009 | 3/31/2009 |
|
PD Weekly Public Notice | 4/7/2009 | 4/7/2009 |
|
Final Order Issued | 5/8/2009 | 5/8/2009 |
|
Certificate Confirming Issued | 8/28/2009 | 8/28/2009 |
|
Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
CBU Due | 10/1/2011 | 10/1/2011 |
|