Process Step | Date Initiated | Date Completed | Comments |
Received | 1/20/2009 | 1/20/2009 |
|
ODFW Review | 1/29/2009 | 5/6/2009 |
|
WMR Request | 1/29/2009 | 4/28/2009 |
|
Transfer Initial Comment Period | 2/3/2009 | 2/3/2009 |
|
Reimbursement Authority | 4/14/2009 | 9/23/2009 |
|
RA Applicant Agreement | 5/13/2009 | 5/13/2009 |
Work Order #: R09 245 09
|
Draft PD Issued | 6/10/2009 | 6/10/2009 |
|
PD Issued | 7/21/2009 | 7/21/2009 |
|
PD Weekly Public Notice | 7/28/2009 | 7/28/2009 |
|
Final Order Issued | 9/23/2009 | 9/23/2009 |
|
Certificate Remaining Issued | 9/23/2009 | |
RR Cert 85694 issued superseded Cert 82929 - 85694 superseded by 86108
RR Cert 85695 issued superseded Cert 80761
|
Completion Due (C Date) | 10/1/2010 | 10/1/2010 |
|
CBU Due | 10/1/2011 | 10/1/2011 |
|
CBU Received | 5/3/2012 | 5/3/2012 |
|
Extension FO Issued | 6/6/2012 | 6/6/2012 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
Proposed Certificate Mailing | 8/16/2013 | 8/16/2013 |
|
Certificate Confirming Issued | 2/28/2014 | 2/28/2014 |
|