| Process Step | Date Initiated | Date Completed | Comments |
| Received | 2/26/2009 | 2/26/2009 |
|
| WMR Request | 3/4/2009 | 3/19/2009 |
|
| ODFW Review | 3/4/2009 | 3/11/2009 |
|
| Transfer Initial Comment Period | 3/10/2009 | 3/10/2009 |
|
| Reimbursement Authority | 3/16/2009 | 10/30/2009 |
|
| RA Applicant Agreement | 4/17/2009 | 4/17/2009 |
Work Order #: R09 239 09
|
| Draft PD Issued | 7/13/2009 | 7/13/2009 |
|
| PD Issued | 9/10/2009 | 9/10/2009 |
|
| PD Weekly Public Notice | 9/15/2009 | 9/15/2009 |
|
| Final Order Issued | 10/30/2009 | 10/30/2009 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Received | 9/12/2012 | 9/12/2012 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Proposed Certificate Mailing | 5/7/2013 | 5/8/2013 |
|
| Proposed Certificate Mailing | 5/7/2013 | 5/8/2013 |
|
| Certificate Confirming Issued | 12/31/2013 | 12/31/2013 |
|