Process Step | Date Initiated | Date Completed | Comments |
Received | 3/12/2009 | 3/12/2009 |
|
WMR Request | 3/17/2009 | 4/8/2009 |
|
ODFW Review | 3/17/2009 | 6/17/2009 |
|
Transfer Initial Comment Period | 3/24/2009 | 3/24/2009 |
|
Deficiency Letter | 1/8/2010 | |
|
Transfer Initial Comment Period | 3/15/2011 | 3/15/2011 |
|
Draft PD Issued | 4/15/2011 | 4/15/2011 |
|
PD Issued | 5/27/2011 | 5/27/2011 |
|
PD Weekly Public Notice | 5/31/2011 | 5/31/2011 |
|
Final Order Issued | 8/29/2011 | 8/29/2011 |
|
CBU Received | 1/3/2012 | 1/3/2012 |
|
Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
CBU Due | 10/1/2013 | 10/1/2013 |
|
Certificate Confirming Issued | 7/30/2021 | 7/30/2021 |
|