Process Step | Date Initiated | Date Completed | Comments |
Received | 3/18/2009 | 3/18/2009 |
|
WMR Request | 3/25/2009 | 4/13/2009 |
|
GW Review Request | 4/1/2009 | 4/28/2009 |
|
Reimbursement Authority | 4/3/2009 | 6/7/2010 |
|
Transfer Initial Comment Period | 4/7/2009 | 4/7/2009 |
|
RA Applicant Agreement | 9/28/2009 | 9/28/2009 |
|
Draft PD Issued | 2/25/2010 | 2/25/2010 |
|
PD Issued | 4/28/2010 | 4/28/2010 |
|
PD Weekly Public Notice | 5/4/2010 | 5/4/2010 |
|
Final Order Issued | 6/7/2010 | 6/7/2010 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Received | 8/2/2012 | 8/2/2012 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Proposed Certificate Mailing | 6/19/2013 | 6/19/2013 |
|
Certificate Confirming Issued | 12/31/2013 | 12/31/2013 |
|