| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/17/2009 | 3/17/2009 |
|
| WMR Request | 3/25/2009 | 3/31/2009 |
|
| Transfer Initial Comment Period | 4/7/2009 | 5/8/2009 |
|
| Deficiency Letter | 9/17/2009 | |
|
| Deficiency Letter | 9/23/2009 | |
|
| Draft PD Issued | 9/30/2016 | 9/30/2016 |
|
| Draft PD Issued | 3/31/2017 | 3/31/2017 |
|
| PD Weekly Public Notice | 5/16/2017 | 5/16/2017 |
|
| PD Issued | 5/16/2017 | 5/16/2017 |
|
| Final Order Issued | 7/6/2017 | 7/6/2017 |
|
| Certificate Confirming Issued | 7/6/2017 | 7/6/2017 |
CERT 93237 ISSUED SUPERSEDES CERT 83571
|