| Process Step | Date Initiated | Date Completed | Comments |
| Received | 3/23/2009 | 3/23/2009 |
|
| WMR Request | 3/25/2009 | 4/13/2009 |
|
| ODFW Review | 3/25/2009 | 4/17/2009 |
|
| Transfer Initial Comment Period | 4/7/2009 | 4/7/2009 |
|
| Reimbursement Authority | 4/9/2009 | 10/30/2009 |
|
| RA Applicant Agreement | 4/29/2009 | 4/29/2009 |
Work Order #: R09 243 09
|
| Draft PD Issued | 6/10/2009 | 6/10/2009 |
|
| PD Issued | 7/16/2009 | 7/16/2009 |
|
| PD Weekly Public Notice | 7/21/2009 | 7/21/2009 |
|
| Final Order Issued | 10/30/2009 | 10/30/2009 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Received | 12/15/2011 | 12/15/2011 |
|
| Certificate Confirming Issued | 4/20/2012 | 4/20/2012 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|