Process Step | Date Initiated | Date Completed | Comments |
Received | 3/30/2009 | 3/30/2009 |
|
WMR Request | 4/10/2009 | 5/14/2009 |
|
GW Review Request | 4/10/2009 | 6/3/2009 |
|
Transfer Initial Comment Period | 4/21/2009 | 4/21/2009 |
|
Draft PD Issued | 8/18/2009 | 8/18/2009 |
|
PD Issued | 9/4/2009 | 9/4/2009 |
|
PD Weekly Public Notice | 9/15/2009 | 9/15/2009 |
|
Final Order Issued | 11/12/2009 | 11/12/2009 |
|
Extension Application Received | 4/16/2012 | 4/16/2012 |
|
Extension FO Issued | 4/19/2012 | 4/19/2012 |
|
Completion Due (C Date) | 10/1/2013 | 10/1/2013 |
|
Extension Application Received | 5/15/2014 | 5/15/2014 |
|
Extension FO Issued | 6/6/2014 | 6/6/2014 |
|
Completion Due (C Date) | 6/6/2014 | 10/1/2018 |
|
CBU Due | 10/1/2014 | 10/1/2014 |
|
CBU Received | 12/9/2019 | 12/9/2019 |
|
Certificate Confirming Issued | 6/3/2022 | 6/3/2022 |
|