Process Step | Date Initiated | Date Completed | Comments |
Received | 4/22/2009 | 4/22/2009 |
|
WMR Request | 5/1/2009 | 5/6/2009 |
|
ODFW Review | 5/1/2009 | 9/30/2009 |
|
Transfer Initial Comment Period | 5/5/2009 | 5/5/2009 |
|
Reimbursement Authority | 5/11/2009 | 1/26/2010 |
|
RA Applicant Agreement | 7/2/2009 | 7/2/2009 |
|
Draft PD Issued | 10/1/2009 | 10/1/2009 |
|
PD Issued | 12/14/2009 | 12/14/2009 |
|
PD Weekly Public Notice | 12/22/2009 | 12/22/2009 |
|
Final Order Issued | 1/26/2010 | 1/26/2010 |
|
Certificate Remaining Issued | 1/26/2010 | |
RR Cert 86051 issued supersedes Cert 51703
RR Cert 86052 issued supersedes Cert 83991
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
CBU Received | 10/9/2012 | 10/9/2012 |
|
Certificate Confirming Issued | 7/8/2013 | 7/8/2013 |
|