| Process Step | Date Initiated | Date Completed | Comments |
| Received | 4/30/2009 | 4/30/2009 |
|
| ODFW Review | 5/1/2009 | 5/21/2009 |
|
| WMR Request | 5/1/2009 | 5/16/2009 |
|
| Transfer Initial Comment Period | 5/5/2009 | 5/5/2009 |
|
| Reimbursement Authority | 1/15/2010 | |
|
| RA Applicant Agreement | 2/23/2010 | 2/23/2010 |
|
| Deficiency Letter | 3/25/2010 | 4/1/2010 |
|
| Draft PD Issued | 5/7/2010 | 5/7/2010 |
|
| PD Issued | 5/21/2010 | 5/21/2010 |
|
| PD Weekly Public Notice | 5/25/2010 | 5/25/2010 |
|
| Certificate Remaining Issued | 6/25/2010 | 6/25/2010 |
RR 86383 supersedes Certificate 39728
RR 86384 supersedes Certificate 67753
|
| Final Order Issued | 6/25/2010 | 6/25/2010 |
|
| CBU Received | 7/6/2010 | 7/6/2010 |
|
| Extension FO Issued | 9/21/2011 | 9/21/2011 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Certificate Confirming Issued | 6/28/2013 | 6/28/2013 |
|
| Certificate Confirming Issued | 6/28/2013 | 6/28/2013 |
|