| Process Step | Date Initiated | Date Completed | Comments |
| Received | 5/6/2009 | 5/6/2009 |
|
| WMR Request | 5/21/2009 | 3/9/2010 |
|
| ODFW Review | 5/21/2009 | 3/15/2010 |
|
| Transfer Initial Comment Period | 5/26/2009 | 5/26/2009 |
|
| Draft PD Issued | 3/1/2010 | 3/15/2010 |
|
| PD Issued | 7/14/2010 | 7/14/2010 |
|
| PD Weekly Public Notice | 7/20/2010 | 7/20/2010 |
|
| Final Order Issued | 9/8/2010 | 9/8/2010 |
|
| CBU Received | 9/22/2011 | 9/22/2011 |
|
| Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
| CBU Due | 10/1/2012 | 10/1/2012 |
|
| Certificate Confirming Issued | 10/11/2013 | 10/11/2013 |
|