Process Step | Date Initiated | Date Completed | Comments |
Received | 5/15/2009 | 5/15/2009 |
|
WMR Request | 5/21/2009 | 6/16/2009 |
|
Transfer Initial Comment Period | 5/26/2009 | 5/26/2009 |
|
Draft PD Issued | 2/19/2010 | 2/19/2010 |
|
PD Issued | 4/1/2010 | 4/1/2010 |
|
PD Weekly Public Notice | 4/6/2010 | 4/6/2010 |
|
Final Order Issued | 5/19/2010 | 5/19/2010 |
|
CBU Received | 8/17/2010 | 8/17/2010 |
|
Certificate Confirming Issued | 12/7/2010 | 12/7/2010 |
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|