| Process Step | Date Initiated | Date Completed | Comments |
| Received | 6/26/2009 | 6/26/2009 |
|
| WMR Request | 7/6/2009 | 7/13/2009 |
|
| GW Review Request | 7/6/2009 | 7/16/2009 |
|
| Reimbursement Authority | 7/8/2009 | 6/13/2011 |
|
| Transfer Initial Comment Period | 7/14/2009 | 7/14/2009 |
|
| RA Applicant Agreement | 10/19/2009 | 10/19/2009 |
|
| Draft PD Issued | 3/23/2011 | 3/23/2011 |
|
| PD Issued | 4/21/2011 | 4/21/2011 |
|
| PD Weekly Public Notice | 4/26/2011 | 4/26/2011 |
|
| Certificate Remaining Issued | 6/13/2011 | |
RR Cert 87099 issued supercedes 85977 -
RR Cert 87100 issued supercedes 80952-
|
| Final Order Issued | 6/13/2011 | 6/13/2011 |
|
| Completion Due (C Date) | 10/1/2012 | 10/1/2012 |
|
| CBU Due | 10/1/2013 | 10/1/2013 |
|