Process Step | Date Initiated | Date Completed | Comments |
Received | 6/30/2009 | 6/30/2009 |
|
Reimbursement Authority | 7/1/2009 | 6/15/2010 |
|
WMR Request | 7/6/2009 | 7/16/2009 |
|
GW Review Request | 7/6/2009 | 7/20/2009 |
|
Transfer Initial Comment Period | 7/14/2009 | 7/14/2009 |
|
RA Applicant Agreement | 2/4/2010 | 2/4/2010 |
|
Draft PD Issued | 2/25/2010 | 2/25/2010 |
|
PD Issued | 4/8/2010 | 4/8/2010 |
|
PD Weekly Public Notice | 4/13/2010 | 4/13/2010 |
|
Final Order Issued | 6/15/2010 | 6/15/2010 |
|
Certificate Remaining Issued | 6/15/2010 | |
RR Cert 86359 issued supersedes Cert 85494
|
Completion Due (C Date) | 10/1/2011 | 10/1/2011 |
|
CBU Received | 8/28/2012 | 8/28/2012 |
|
CBU Due | 10/1/2012 | 10/1/2012 |
|
Certificate Confirming Issued | 12/20/2013 | 12/20/2013 |
|