Process Step | Date Initiated | Date Completed | Comments |
Received | 7/29/2009 | 7/29/2009 |
|
Transfer Initial Comment Period | 8/18/2009 | 9/18/2009 |
|
WMR Request | 8/18/2009 | 2/2/2010 |
|
GW Review Request | 8/18/2009 | 10/29/2009 |
|
Deficiency Letter | 2/23/2010 | 7/21/2010 |
|
Administrative Hold | 2/16/2011 | 9/14/2011 |
|
Draft PD Issued | 9/14/2011 | 9/14/2011 |
|
PD Issued | 11/28/2011 | 11/28/2011 |
|
PD Weekly Public Notice | 11/29/2011 | 11/29/2011 |
|
Final Order Issued | 12/21/2012 | 12/21/2012 |
|
Certificate Remaining Issued | 12/21/2012 | 12/21/2012 |
CERTIFICATE 87869 AND 87868 ISSUED TO SUPERSEDE 30302 AND 83034 RESPECTIVELY
|
Certificate Remaining Issued | 2/14/2013 | 2/14/2013 |
RR Cert 87932 issued supersedes Cert 83893
|
CBU Due | 10/1/2015 | 10/1/2015 |
|
Completion Due (C Date) | 10/1/2016 | 10/1/2016 |
|