Process Step | Date Initiated | Date Completed | Comments |
Received | 7/31/2009 | 7/31/2009 |
|
Transfer Initial Comment Period | 8/18/2009 | 8/18/2009 |
|
WMR Request | 8/20/2009 | 10/27/2009 |
|
ODFW Review | 8/20/2009 | 10/14/2009 |
|
Draft PD Issued | 11/28/2011 | 11/28/2011 |
|
Administrative Hold | 12/28/2011 | 1/13/2012 |
|
Final Order Issued | 1/5/2012 | 1/5/2012 |
|
Reconsideration Requested | 2/9/2012 | 2/14/2012 |
|
Final Order Issued | 2/14/2012 | 2/14/2012 |
|
Draft PD Issued | 5/3/2012 | 5/3/2012 |
|
News $ Due Letter | 5/3/2012 | 11/29/2012 |
|
Administrative Hold | 5/21/2012 | 7/6/2012 |
|
Draft PD Issued | 10/25/2012 | 10/25/2012 |
|
PD Issued | 12/4/2012 | 12/4/2012 |
|
PD Weekly Public Notice | 12/11/2012 | 12/11/2012 |
|
Consent to Injury Review Requested | 12/11/2012 | 12/11/2012 |
|
Consent to Injury Review Requested | 2/1/2013 | 2/1/2013 |
|
CTI Recommendation Comment Period | 3/12/2013 | 4/12/2013 |
|
Certificate Remaining Issued | 5/8/2013 | 5/8/2013 |
RR Cert 88197 issued supersedes Cert 12096
|
Final Order Issued | 5/8/2013 | 5/8/2013 |
|
Completion Due (C Date) | 5/16/2013 | 10/1/2014 |
|
CBU Due | 5/16/2013 | 10/1/2015 |
|
CBU Received | 10/2/2015 | 10/2/2015 |
|
Certificate Confirming Issued | 3/25/2022 | 3/25/2022 |
|